Process Chemicals has been engaged by Downer & JKC to conduct pre-commissioning scope of work, undertaking lube oil flushing & chemical cleaning activities on all major pipework & cooling systems for the Combined Cycle Power Plant (CCP-2) elements. These include: GE vendor supplied Gas turbine generators (GTG’s) & Steam turbine generators (STG’s) along with Boiler feed & condenser equipment. Project timeline is approximately 12 months.